Transportation

Stevens Creek Trail extension study near Mountain View High School

Dale Avenue & Heatherstone Way toward West Remington Drive

Stevens Creek Trail Extension, Dale Avenue/Heatherstone Way to West Remington Drive · CIP 20-50

Study
What you can do now

Dale Avenue & Heatherstone Way toward West Remington Drive

What’s changing

A study will compare trail alignments toward West Remington Drive and a proposed walking and biking bridge over Highway 85 near Mountain View High School.

  • This project covers roughly 0.8 miles from the existing trail endpoint at Dale/Heatherstone to West Remington in Sunnyvale. Sunnyvale’s separate Remington-to-Fremont project is outside this project’s scope.
  • The consultant will study alignments, prepare environmental documents, and support public outreach. A preferred concept would precede 35% design. No final trail alignment or construction start is established here.
  • Council authorized a Sunnyvale funding agreement, acceptance of $600,000, and an $846,500 consultant agreement on May 26, 2026. The September listing says agreement execution is in progress.
  • The staff report estimates this study/design/environmental phase would finish at the beginning of 2029; the September listing says summer 2029. Neither is a confirmed trail-opening date.
Latest documented update

Study agreements authorized

May 26, 2026

The public action history records Council approval of the funding and consultant authorizations, not final trail approval or construction.

The story so far

Selected records
  1. May 26, 2026

    Council decision

    Council authorized funding and consultant agreements

    Council approved the Sunnyvale funding-agreement and professional-services authorizations in File 205835. This advances the feasibility, design and environmental work.

    Read the official record (opens a new tab)

Go to the source

Official records behind this story. Last checked October 22, 2026.

File 205835, May 26, 2026: public action history shows approved / Pass.

Open official source (opens a new tab)

May 26, 2026 report, pages 2–5: Mountain View project limits, separate Sunnyvale project, alignment study, environmental work and planned outreach.

Open official source (opens a new tab)

September 2026 listing: study phase, agreements in progress, estimate and project contact.

Open official source (opens a new tab)