A new park off San Rafael Avenue
939 San Rafael Avenue
San Rafael Park, Design and Construction · CIP 24-36
Project location
Open in Google Maps (opens a new tab)939 San Rafael Avenue
What’s changing
The city is preparing a 2.40-acre park off San Rafael Avenue, with design consultant selection and site clearing still ahead.
- The city expects demolition at 939 San Rafael Avenue in early 2027 and an initial community meeting in summer 2027. Neither has a confirmed date here.
- Additional land at 975 Terra Bella Avenue is planned for a second phase whose design and construction funding has not been allocated. Summer 2030 is the city’s completion estimate.
Design procurement and site clearing planned
September 2026 city listing
The listing reports current preparations. Its update month is not an individual milestone date; the latest linked Council report is June 23, 2026.
The story so far
Selected recordsJune 9, 2026
City-reported milestoneCity reports purchase approval for a later park phase
The Public Works update reports Council approval to buy an additional 0.86 acres at 975 Terra Bella Avenue. Design and construction funding for that second phase has not been allocated.
Read the official record (opens a new tab)
Go to the source
Official records behind this story. Last checked October 15, 2026.
Expand San Rafael Park for the initial park area, preparation, second-phase funding limits, and schedule estimates.
Open official source (opens a new tab)