Transportation

Rengstorff Avenue railroad crossing changes

Rengstorff Avenue & Central Expressway

Rengstorff Avenue Grade Separation · CIP 22-27

Design & right-of-way
What you can do now

Rengstorff Avenue & Central Expressway

What’s changing

Plans would lower the intersection beneath the Caltrain tracks and add new walking, biking, and street connections.

  • The planned road crossing would pass beneath the tracks, with trains remaining near their current elevation.
  • Plans include a bicycle and pedestrian overcrossing, a Leland Avenue connector, and a Crisanto Avenue cul-de-sac.
  • The current city listing reports that 65% design was submitted in May 2026. It also reports a $99 million funding gap.
  • Spring 2029 is the city’s anticipated completion for Phase I, the Leland Avenue realignment. It is not a completion date for the entire crossing.
Latest documented update

Environmental notice posted

September 3, 2026

Latest dated project record found in the sources checked. The notice does not establish a construction start or full funding.

The story so far

Selected records
  1. September 3, 2026

    Published record

    Environmental notice posted

    A state filing describes the planned crossing and associated street connections.

    Read the official record (opens a new tab)
  2. May 2026

    City-reported milestone

    65% design submitted

    The city’s current Public Works listing reports this design milestone. The listing itself is undated.

    Read the official record (opens a new tab)
  3. November 18, 2025

    Council decision

    Council approved cost-reduction measures

    Council approved measures intended to reduce estimated costs by about $58.1 million while retaining the project’s alignment and intent. These are intended savings, not measured construction savings.

    Read the official record (opens a new tab)
  4. September 2, 2025

    Committee recommendation

    Committee recommended cost reductions

    The Transportation Committee recommended measures for Council approval.

    Read the official record (opens a new tab)

Go to the source

Official records behind this story. Last checked October 9, 2026.

Current phase, design milestone, funding gap, and Phase I estimate. Undated listing.

Open official source (opens a new tab)

Posted September 3, 2026. Describes the planned work.

Open official source (opens a new tab)

Agenda item 6.1 and recorded Council action.

Open official source (opens a new tab)

Background information. This page retains an earlier design target; use the highlights listing for the reported phase.

Open official source (opens a new tab)