Rengstorff Avenue railroad crossing changes
Rengstorff Avenue & Central Expressway
Rengstorff Avenue Grade Separation · CIP 22-27
Project location
Open in Google Maps (opens a new tab)Rengstorff Avenue & Central Expressway
What’s changing
Plans would lower the intersection beneath the Caltrain tracks and add new walking, biking, and street connections.
- The planned road crossing would pass beneath the tracks, with trains remaining near their current elevation.
- Plans include a bicycle and pedestrian overcrossing, a Leland Avenue connector, and a Crisanto Avenue cul-de-sac.
- The current city listing reports that 65% design was submitted in May 2026. It also reports a $99 million funding gap.
- Spring 2029 is the city’s anticipated completion for Phase I, the Leland Avenue realignment. It is not a completion date for the entire crossing.
Environmental notice posted
September 3, 2026
Latest dated project record found in the sources checked. The notice does not establish a construction start or full funding.
The story so far
Selected recordsSeptember 3, 2026
Published recordEnvironmental notice posted
A state filing describes the planned crossing and associated street connections.
Read the official record (opens a new tab)May 2026
City-reported milestone65% design submitted
The city’s current Public Works listing reports this design milestone. The listing itself is undated.
Read the official record (opens a new tab)November 18, 2025
Council decisionCouncil approved cost-reduction measures
Council approved measures intended to reduce estimated costs by about $58.1 million while retaining the project’s alignment and intent. These are intended savings, not measured construction savings.
Read the official record (opens a new tab)September 2, 2025
Committee recommendationCommittee recommended cost reductions
The Transportation Committee recommended measures for Council approval.
Read the official record (opens a new tab)
Go to the source
Official records behind this story. Last checked October 9, 2026.
Current phase, design milestone, funding gap, and Phase I estimate. Undated listing.
Open official source (opens a new tab)Posted September 3, 2026. Describes the planned work.
Open official source (opens a new tab)Agenda item 6.1 and recorded Council action.
Open official source (opens a new tab)Background information. This page retains an earlier design target; use the highlights listing for the reported phase.
Open official source (opens a new tab)