Transportation

Street and bike lane changes on Miramonte, Cuesta to Castro

Miramonte Avenue, Cuesta Drive to Castro Street

Miramonte Avenue Pavement Improvement, Segment B · CIP 20-01

Under construction · city listing
What you can do now

Miramonte Avenue, Cuesta Drive to Castro Street

What’s changing

Pavement work changes Miramonte from four lanes to three, adds bike facilities, and updates crossings and sidewalks between Cuesta Drive and Castro Street.

  • The city’s September 2026 listing reports construction. Fall 2026 completion is an estimate, not a confirmed finish date.
  • The scope includes a two-way separated bikeway between Hans Avenue and Castro Street, buffered bike lanes toward Cuesta, curb ramps, sidewalk work, and a crossing beacon at Hans Avenue.
  • This is separate from Segment A, Castro Street to El Camino Real, CIP 25-28, which is in design.
Latest documented update

Construction reported in city listing

September 2026

This is the listing’s update month, not the construction start date. A completion notice has not been verified.

The story so far

Selected records
  1. June 27, 2023

    Council decision

    Council approved the road diet alternative

    The September 23, 2025 staff report records Council’s June 27, 2023 approval of the road diet between Cuesta Drive and Castro Street.

    Read the official record (opens a new tab)

Go to the source

Official records behind this story. Last checked October 22, 2026.

September 2026 listing: Segment B scope, construction phase, completion estimate, and staff contact.

Open official source (opens a new tab)

September 23, 2025 report, pages 1–5: CIP 20-01, Cuesta–Castro scope, location diagram and prior Council decisions. Recommendations for that meeting are not recorded outcomes.

Open official source (opens a new tab)