Transportation

Street and crossing changes along El Monte Avenue

El Monte Avenue, El Camino Real to Springer/Jay, plus El Camino Real to Escuela

El Monte Corridor Improvements · CIP 21-38

Design
What you can do now

El Monte Avenue, El Camino Real to Springer/Jay, plus El Camino Real to Escuela

What’s changing

Plans change El Monte Avenue from four lanes to three, add bike and crossing improvements, and update its connections with El Camino Real and Escuela Avenue.

  • The project covers nine intersections: El Monte Avenue from El Camino Real to Springer Road/Jay Street, plus El Camino Real between Escuela Avenue and El Monte Avenue.
  • The September 2026 city listing reports 65% design under review. Bidding/award authorization in Q2 2027 and completion in fall 2028 are estimates.
  • The Council Transportation Committee approved the preliminary design on September 2, 2025. This does not establish final design approval or a construction start.
  • The standalone project page still carries an older spring 2026 construction estimate. The newer September listing is used here for the reported phase and schedule.
Latest documented update

65% design under review

September 2026

This is the city listing’s update month, not a dated design approval or construction milestone.

The story so far

Selected records
  1. September 2, 2025

    Committee decision

    Committee approved preliminary design

    The Council Transportation Committee approved the preliminary design and advancement toward final design, recorded under File 204723.

    Read the official record (opens a new tab)

Go to the source

Official records behind this story. Last checked October 22, 2026.

September 2026 listing: 65% design, Q2 2027 authorization estimate, fall 2028 completion estimate and staff contact.

Open official source (opens a new tab)

File 204723, September 2, 2025: public committee action history shows approved / Pass.

Open official source (opens a new tab)

September 2, 2025 report, pages 1–4 and 8–9: corridor limits, preliminary design and then-estimated next steps.

Open official source (opens a new tab)